INTERVIEWS AND INFORMATION GATHERING

(Traverse tree in post order)

 

PLAN

Typical Budget : PLAN

  1. Activity Effort Days
  2. Planning 1 to 4
  3. Briefing Sessions 1
  4. Interviews 3*n (n number of individuals)
  5. Model/Remodel 2 to 6
  6. Feedback Preparation 2 to 3
  7. Feedback 2 to 3
  8. Consolidate 2
  9. Conclusions, etc. 4 to 8
  10. Prepare Report 4 to 10
  11. Prepare Presentation 2
  12. Verbal Report 2
  13. Finalize and Deliver 4

REPEAT 5 THROUGH 8 AS MANY TIMES AS NECESSARY (3 to 4 times) TILL AGREEMENT IS REACHED IN FEEDBACK SESSIONS.

At $1,400 consulting fee per day per person, information gathering comes to about $150,000 on a 1.5 million dollar project (about 10% of the budget).

 